Capacity Planning Data

 

The Capacity Planning feature compares information set in several setup areas to what is requested or what is assigned. The information from the setup areas is considered the total amount available or capacity. The data set within MoversSuite Local Services reduces the capacity. Then, Capacity Planning  computes the available amount- or capacity.

 

Refer to the Capacity Planning Setup topic for information on setting the capacity values.

 

The section discusses the MoversSuite data that affects Capacity Planning.

 

Capacity Planning utilizes data set for a Local Services requests through the Add Local Service screen. Packing counts entered through the CPU option, along with Labor Request and Equipment Request amounts, determine the demand. For planning types based on hours, the application references the Service Time, and possibly the Hrs/Man setting as well (see “Hrs/Man” in data table below.)

 

 

Figure 6: Add Local Service screen

 

 

 

 

 

The data referenced is detailed in the following table.

 

Setting

Description

CPU

The estimated Packing counts within Update Containers, Packing and Unpacking are compared to the various packing types. The application compares these counts to what is available for the branch as set within the Daily Packing Capacity Setup.

Types available to Capacity Planning are those with the Packing Capacity Bucket set within Material Type Setup.

Service Date

The date of the service is what Capacity Planning searches by and reports on.

Service Time

Prior to actual assignments in Local Dispatch, hourly personnel and equipment requests are allocated based on the service date spread (refer to the Service Time Evaluation section below for more information).

Hrs/Man

If only the first Service Time date is set, then the application references the Hrs/Man computed (less drive time) based on order values and what is requested for labor and equipment needs.

Labor Request

Counts set within the Labor Request dialog and associated to supported labor types are included in Capacity Planning.

Types available to Capacity Planning are those with the Capacity Bucket set within Labor Type Setup. This represents the estimated labor needed for a given day.

Equipment Request

Counts set within the Equipment Request dialog and associated to supported equipment types are included in Capacity Planning.

Types available to Capacity Planning are those with the Capacity Bucket set within Equipment Type Setup. This represents the estimated labor needed for a given day.

 

 

Local Dispatch Assignment

 

Once assignments are made through Local Dispatch, the application no longer references equipment and labor requests. Instead, Capacity Planning is based on the actual assignments made to determine the need. The application references the following for actual assignments associated to Capacity Planning:

 

Assign Crew

Crew

Enter Actuals

Equipment Times

Equipment Quantities

Reserve Equipment

Set Service Time

Update Containers, Packing and Unpacking

 

 

Default Branch

 

When equipment and personnel assignments are made, the application references those resources and crew that have a Default Branch set on the Equipment Setup or Personnel Setup record that matches that which was selected through Capacity Planning.

 

NOTE:  The application also considers all branches within the Dispatching Common View when displaying information on the selected branch within the Capacity Planning page.

 

If a resource or person is assigned to a service that is not its Default Branch (or within its Dispatching Common View), then the application reduces capacity for their Default Branch. For example, if the Default Branch of a driver is AAA and they are assigned to a service on branch BBB, then the capacity for branch AAA is reduced by the number of hours (or the count) assigned to BBB.

 

 

Service Time Evaluation

 

Capacity Planning evaluates times for equipment and personnel differently depending on where the service is at in the process. If assignments have been made through Local Dispatch, then the job start and end times are considered. Otherwise, the application references the requested times entered for the service within Add Local Service.

 

If only the requested start time is set, then the hours per man (Hrs/Man) is referenced, assuming that the service is completed on the same day.

 

If the time range crosses the midnight boundary, then times are split into separate days.

 

 

Rounding

 

Capacity Planning is designed as an estimating tool; therefore, data is rounded. This affects how hours are calculated because often the need/use includes partial hours, such as 30 minutes. This is unlike materials, where a whole box is either used or not used and is easily calculated.

 

When computing the Used Capacity in hours, the application rounds up to the next hour. So, if the total service time needed for a given day is 41 hours and 53 minutes, the application rounds the need to 42 hours. Likewise, if the total is 41 hours and 13 minutes, the application still rounds up to 42 hours.

 

Similarly, percentages that display for % of Capacity Used are also rounded up to the next highest whole number.

 

The opposite is true when calculating Available Capacity, or the remaining hours available. Hours are rounded down to the next hour. So, if the total available amount of labor on a given day is 35 hours and 30 minutes, the application rounds this down to 35 hours. This is because 36 hours are not available - 35 hours are available. This chart only uses whole numbers so rounding down ensures capacity is not exceeded.

 

The overall idea behind these calculations is the “Capacity Bucket”. Each bucket has a set number of items in it and that is the bucket’s capacity. As items are used, they are put in the Used Capacity bucket. To continue the analogy, let’s pretend each item is represented by a tennis ball and our bucket has a capacity of 10 tennis balls. Then, if 5 1/2 tennis balls were needed, you need to “use” 6 tennis balls for the 5 1/2 needed - 5 is not enough. Now, when thinking about Available Capacity, or the remaining capacity, if 4 1/2 tennis balls are still available when the system makes its calculations, it rounds down to 4 being available.  Since only whole numbers are used in this chart, it cannot show 4 1/2 being available.

 

IMPORTANT:  Remember that this is an estimating tool. We want to minimize the effects of rounding and never over calculate availability, i.e., err on the side of caution.